1Z0-1129 practice question 6 of 10

What is the purpose of drag-and-drop functionality in the WBS tab?

Full set: 429 questions
Answer options
A:

A. Assign resources

B:

B. Rearrange WBS elements within the hierarchy

Correct answer
C:

C. Create activity codes

D:

D. Define baseline schedules

Correct Answer:
B. B. Rearrange WBS elements within the hierarchy
Explanation

In Oracle Primavera Cloud, the Work Breakdown Structure (WBS) tab provides a hierarchical representation of a project's deliverables and phases. The drag-and-drop functionality within this tab is specifically designed to allow users to easily rearrange WBS elements within the hierarchy. By clicking and dragging a WBS node, a user can change its sequence among sibling nodes or move it under a completely different parent node. This intuitive interface allows project managers to restructure the project's framework efficiently without needing to manually edit parent identifiers or use complex menu commands.

Why Incorrect

A. Assign resources: Resources are assigned to activities or WBS nodes using the Resource Assignment panels or dedicated tabs, not via drag-and-drop in the WBS hierarchy view.
C. Create activity codes: Activity codes are created and managed in the workspace or project Dictionaries, not by dragging and dropping elements in the WBS tab.
D. Define baseline schedules: Baselines are created, managed, and assigned through the Schedule and Baselines management features, which are entirely separate from WBS drag-and-drop actions.

References

1. Oracle Corporation. (2023). Oracle Primavera Cloud Help: Project Schedule Management. "Create a WBS" - Section: Working with the WBS Hierarchy.

2. Oracle Corporation. (2023). Oracle Primavera Cloud User Guide. Chapter: WBS and Activities, Topic: Rearranging WBS Nodes.

Scroll to Top