1Z0-1129 practice question 6 of 10
What is the purpose of drag-and-drop functionality in the WBS tab?
Full set: 429 questionsIn Oracle Primavera Cloud, the Work Breakdown Structure (WBS) tab provides a hierarchical representation of a project's deliverables and phases. The drag-and-drop functionality within this tab is specifically designed to allow users to easily rearrange WBS elements within the hierarchy. By clicking and dragging a WBS node, a user can change its sequence among sibling nodes or move it under a completely different parent node. This intuitive interface allows project managers to restructure the project's framework efficiently without needing to manually edit parent identifiers or use complex menu commands.
A. Assign resources: Resources are assigned to activities or WBS nodes using the Resource Assignment panels or dedicated tabs, not via drag-and-drop in the WBS hierarchy view.
C. Create activity codes: Activity codes are created and managed in the workspace or project Dictionaries, not by dragging and dropping elements in the WBS tab.
D. Define baseline schedules: Baselines are created, managed, and assigned through the Schedule and Baselines management features, which are entirely separate from WBS drag-and-drop actions.
1. Oracle Corporation. (2023). Oracle Primavera Cloud Help: Project Schedule Management. "Create a WBS" - Section: Working with the WBS Hierarchy.
2. Oracle Corporation. (2023). Oracle Primavera Cloud User Guide. Chapter: WBS and Activities, Topic: Rearranging WBS Nodes.
Keep practicing
Take the free 1Z0-1129 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1129 practice questions
- Question 1How can labor units be updated for tasks in Primavera P6?
- Question 2What is the purpose of tracking utilization percentages in the Analysis Page?
- Question 3What two steps are required to create a baseline in Primavera P6?
- Question 4What two features does the Maintain Baselines tool offer?
- Question 5What two factors determine the choice of calendar for an activity?
- Question 7What two actions are possible when using the drag-and-drop functionality in the WBS tab?