1Z0-1129 practice question 7 of 10
What two actions are possible when using the drag-and-drop functionality in the WBS tab?
Full set: 429 questionsThe drag-and-drop feature in the Oracle Primavera Cloud WBS tab is utilized to visually manage and organize the structural layout of a project. By using this functionality, users can perform two primary actions: moving WBS elements within the hierarchy (which changes their display order or sequence among peers) and rearranging parent-child relationships (such as moving a child node to a new parent node or altering its indentation level). This streamlines the organization of project deliverables during the planning phase.
B. Assign resources to WBS elements: Resource assignment is handled through dedicated assignment dialogs, detail windows, or the Resources tab, not by dragging and dropping within the WBS structure tab.
D. Modify activity durations: Activity durations are modified within the Activities page, schedule grid, or activity details panel, not within the WBS hierarchy tab.
1. Oracle Corporation. (2023). Oracle Primavera Cloud Help: Project Schedule Management. "Create a WBS" - Section: Working with the WBS Hierarchy.
2. Oracle Corporation. (2023). Oracle Primavera Cloud User Guide. Chapter: WBS and Activities, Topic: Rearranging WBS Nodes and Parent-Child Relationships.
Keep practicing
Take the free 1Z0-1129 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1129 practice questions
- Question 1How can labor units be updated for tasks in Primavera P6?
- Question 2What is the purpose of tracking utilization percentages in the Analysis Page?
- Question 3What two steps are required to create a baseline in Primavera P6?
- Question 4What two features does the Maintain Baselines tool offer?
- Question 5What two factors determine the choice of calendar for an activity?
- Question 6What is the purpose of drag-and-drop functionality in the WBS tab?