1Z0-1129 practice question 5 of 10

What two factors determine the choice of calendar for an activity?

Full set: 429 questions
Answer options
A: Type of task and its dependency
B: Resource availability Correct answer
C: Project deadlines
D: Non-working day exceptions Correct answer
Correct Answer:
B. Resource availability; D. Non-working day exceptions
Explanation

Selecting the appropriate calendar for an activity in Primavera P6 depends on resource availability and non-working day exceptions. Resource availability ensures tasks align with the specific work shifts and working hours of assigned labor or equipment, while non-working day exceptions account for project site closures, weather constraints, and corporate or national holidays.

Why Incorrect

A. Task dependencies define sequential relationships between activities, whereas calendars define working and non-working time availability.
C. Project deadlines set target finish constraints but do not determine the daily working hours or calendar rules applied to activities.

References

- Oracle Primavera P6 EPPM Project Management Guide, Section: "Defining and Assigning Activity Calendars", Oracle Documentation.

- Oracle Primavera P6 Professional User Guide, Section: "Creating Calendars", Oracle Help Center.