What two factors determine the choice of calendar for an activity?
Full set: 429 questionsSelecting the appropriate calendar for an activity in Primavera P6 depends on resource availability and non-working day exceptions. Resource availability ensures tasks align with the specific work shifts and working hours of assigned labor or equipment, while non-working day exceptions account for project site closures, weather constraints, and corporate or national holidays.
A. Task dependencies define sequential relationships between activities, whereas calendars define working and non-working time availability.
C. Project deadlines set target finish constraints but do not determine the daily working hours or calendar rules applied to activities.
- Oracle Primavera P6 EPPM Project Management Guide, Section: "Defining and Assigning Activity Calendars", Oracle Documentation.
- Oracle Primavera P6 Professional User Guide, Section: "Creating Calendars", Oracle Help Center.
Keep practicing
Take the free 1Z0-1129 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1129 practice questions
- Question 1How can labor units be updated for tasks in Primavera P6?
- Question 2What is the purpose of tracking utilization percentages in the Analysis Page?
- Question 3What two steps are required to create a baseline in Primavera P6?
- Question 4What two features does the Maintain Baselines tool offer?
- Question 6What is the purpose of drag-and-drop functionality in the WBS tab?
- Question 7What two actions are possible when using the drag-and-drop functionality in the WBS tab?