1Z0-1129 practice question 3 of 10

What two steps are required to create a baseline in Primavera P6?

Full set: 429 questions
Answer options
A: Open the project exclusively
B: Select Project > Maintain Baselines Correct answer
C: Define baseline start and finish dates
D: Assign the baseline to the project Correct answer
Correct Answer:
B. Select Project > Maintain Baselines; D. Assign the baseline to the project
Explanation

To create a baseline in Primavera P6, one must first open the project exclusively (A) to prevent access conflicts. Then, the project manager selects Project > Maintain Baselines (B) to set the baseline. Finally, assigning the baseline to the project (D) makes it the reference for tracking progress.

Why Incorrect

A. Opening the project exclusively is not a mandatory step for creating a baseline; it primarily helps avoid conflicts.
C. Defining baseline start and finish dates is not necessary; the selecting and assigning steps cover this.

References

- Primavera P6 User Guide, Oracle. (2021). Project Management Features, pp. 79-81.

- Primavera P6 Fundamentals Training Manual, Oracle. (2020). Baseline Creation, pp. 23-25.

- Primavera P6 Documentation, Oracle. (2022). User Preferences and Baselines, §4.3.