1Z0-1129 practice question 10 of 10
What does the Schedule Performance Index (SPI) measure?
Full set: 429 questionsThe Schedule Performance Index (SPI) measures the efficiency of schedule progress by comparing the earned value (EV) to the planned value (PV), which reflects how efficiently work is being completed relative to the project's schedule baseline.
B. Total float is unrelated to SPI; it measures scheduling flexibility, not efficiency.
C. Resource utilization variance doesn't directly relate to schedule efficiency as described by SPI.
D. SPI focuses on overall progress, not just critical activities.
1. PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 6th Edition. Section 7.4.1.2.
2. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 12th Edition. Chapter 23, pp. 584-589.
3. Mulcahy, R. (2018). Creating a Winning Project Portfolio. Gower Publishing. DOI: https://doi.org/10.4324/9781351227519.
4. Oracle. (2020). Oracle Primavera P6 Enterprise Project Portfolio Management. Documentation on Performance Index metrics.
5. PM Solutions. (2015). Managing Project Performance. Section on Performance Metrics.
Keep practicing
Take the free 1Z0-1129 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1129 practice questions
- Question 1How can labor units be updated for tasks in Primavera P6?
- Question 2What is the purpose of tracking utilization percentages in the Analysis Page?
- Question 3What two steps are required to create a baseline in Primavera P6?
- Question 4What two features does the Maintain Baselines tool offer?
- Question 5What two factors determine the choice of calendar for an activity?
- Question 6What is the purpose of drag-and-drop functionality in the WBS tab?