AD0-E903 practice question 11 of 15
Which field is used to create a milestone step on a milestone path in the Setup area?
Full set: 70 questionsA milestone step within a Milestone Path represents a specific system status. When a system administrator creates a new project status in the Adobe Workfront Setup area, the "Key" is a mandatory and unique field. This key serves as the system's internal, immutable identifier for that status. While a user might select a status by its name in the user interface when building the milestone path, the underlying "Key" is the fundamental field that uniquely defines the status object, enabling its creation and subsequent use as a milestone step.
A. Status: This term is too general. A milestone step is a status, but "Key" is the specific, unique identifier field required to create the status object in the system's backend.
B. Description: This field is used for providing optional, supplementary text about the status or milestone. It is not a required or identifying field for its creation.
1. Adobe Workfront Documentation, "Create and edit statuses": This document explicitly details the fields required to create a new status. It states, "Key: This is a required field. The key is used to identify the status in the database. The key is not visible in the user interface to all users... We recommend that you use a key that is relevant to the name of the status." This confirms the "Key" is the fundamental identifier for the status object. (Adobe Experience League, Workfront Documentation, Setup > Project Preferences > Statuses section).
2. Adobe Workfront Documentation, "Create a milestone path": This guide explains that a milestone path is a sequence of system statuses. It notes, "A milestone path is a series of statuses that a project goes through from start to finish." When adding a milestone, you select a "System Status." This establishes that the milestone step is a direct application of a status object, which is fundamentally defined by its "Key" as per the first reference. (Adobe Experience League, Workfront Documentation, Setup > Project Preferences > Milestone Paths section).
Keep practicing
Take the free AD0-E903 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AD0-E903 practice questions
- Question 1Which two options are available with Workfront reports? (Choose two.)
- Question 2A marketing team determines that in the future, their projects must be reviewed by the Pr…
- Question 3Which project Condition is set when the Progress Status of the project is Behind or At Ri…
- Question 4What are two ways to associate milestone steps to tasks? (Choose two.)
- Question 5A team member has five days to complete a critical path task, and the task requires only …
- Question 6How would a project manager create a custom Workfront report to show information about is…