AD0-E903 practice question 12 of 15
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied. Which date type would the project manager utilize?
Full set: 70 questionsThe Projected Date in Adobe Workfront is a system-calculated forecast that indicates when a task is likely to be completed. This calculation is dynamic, taking into account the task's current progress (percent complete), its duration, and the completion status of all its predecessors. It provides a real-time, realistic completion timeline based on actual work performed, which is precisely what the project manager requires. This date is distinct from the Planned Date, which represents the original schedule.
A. Estimated Date: This term typically refers to an initial assessment of effort or duration (e.g., Estimated Hours) rather than a specific, system-calculated completion date that dynamically updates with progress.
C. Planned Date: This is the static, baseline date established during the project planning phase. It does not automatically change to reflect current progress or delays from predecessors.
1. Adobe Workfront Documentation
"Overview of the Projected Completion Date for projects
tasks
and issues": "The Projected Completion Date is the date when the project
task
or issue is expected to be completed. Adobe Workfront calculates this date based on the progress of the project and its tasks
as well as any preceding items." (Section: "How Workfront calculates the Projected Completion Date"). This source directly confirms that the Projected Date is calculated based on progress and predecessors.
2. Adobe Workfront Documentation
"Planned Completion Date overview": "The Planned Completion Date of a task is the date when the task is scheduled to be completed. You can manually specify the Planned Completion Date of a task or Adobe Workfront can calculate it based on the project Planned Start Date and the predecessor relationships in the project." (Section: "Planned Completion Date overview"). This highlights that the Planned Date is part of the schedule
not a forecast based on current progress.
3. Adobe Workfront Documentation
"Glossary of Adobe Workfront terminology":
Projected Dates: "The dates when work is likely to start or finish
based on earlier items in the plan that have already started or finished."
Planned Dates: "The dates when work is scheduled to start or finish
according to the original plan."
This glossary clearly distinguishes between the scheduled (Planned) and the likely/forecasted (Projected) dates.
Keep practicing
Take the free AD0-E903 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AD0-E903 practice questions
- Question 1Which two options are available with Workfront reports? (Choose two.)
- Question 2A marketing team determines that in the future, their projects must be reviewed by the Pr…
- Question 3Which project Condition is set when the Progress Status of the project is Behind or At Ri…
- Question 4What are two ways to associate milestone steps to tasks? (Choose two.)
- Question 5A team member has five days to complete a critical path task, and the task requires only …
- Question 6How would a project manager create a custom Workfront report to show information about is…
