APM-PFQ practice question 28 of 35

During the consideration of when and how the development of the project management plan should take place, the objectives of carrying out such an exercise can often appear to be uncertain. As a recommendation, the project management plan should be:

Full set: 409 questions
Answer options
A: assembled when all information is available.
B: developed iteratively throughout the early stages of the project. Correct answer
C: completed in detail before the project is authorised.
D: free from detailed schedule information.
Correct Answer:
B. developed iteratively throughout the early stages of the project.