APM-PFQ practice question 27 of 35

Which one of the following statements about the project management plan (PMP) is FALSE?

Full set: 409 questions
Answer options
A: The PMP acts as a contract between the Project Manager, the project team and the sponsor.
B: The PMP defines the baselines for the project upon which changes are considered.
C: The PMP, once defined, will remain unchanged throughout the project. Correct answer
D: The PMP is used as a reference document for managing the project.
Correct Answer:
C. The PMP, once defined, will remain unchanged throughout the project.