Which of the following are not typical responses to risks?
Complete root cause analysis to understand why the situation has occurred.
Reduce the probability of the threat occurring or the impact on the project.
Change objectives or practices to change the cause of the threat so it can no longer occur.
There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any
residual risk must be managed.
Prepare a risk management plan to document the risk and give it to your sponsor.
Pass the responsibility for bearing the impact of the threat from one party to another.
Question 10 of 10
Keep practicing
Take the free APM-PMQ practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other APM-PMQ practice questions
- Question 1Which of the following statements does not describe the importance of linking projects to…
- Question 2You are in the design phase of a project to deliver offices on a newly acquired plot of l…
- Question 4During a project review, which of the following would be the best indicator of how the pr…
- Question 5You are the project manager on a construction project for a client in the defence sector.…
- Question 6Which of the activities below would provide final assurance of a project?
- Question 7You are a project manager leading a newly formed project team. Which factor should NOT in…