CCP practice question 21 of 25
After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is…
Full set: 189 questionsThe project's percent complete is a core metric in Earned Value Management (EVM) and is calculated by dividing the Earned Value (EV) by the Budget at Completion (BAC). Based on the data provided, the EV is 105,000 work hours, and the BAC is 200,000 work hours. The correct calculation is: Percent Complete = (EV / BAC) 100 Percent Complete = (105,000 / 200,000) 100 = 52.5% Therefore, the contractor's stated progress of 60% is incorrect. The actual, earned progress is 52.5%.
A. No, it should be 55.0% This value is derived from Actual Cost / Budget at Completion (110,000 / 200,000), which represents the percentage of the budget spent, not the physical work completed.
B. No, it should be 50.0% This value is derived from Planned Value / Budget at Completion (100,000 / 200,000), which represents the planned progress, not the actual progress achieved to date.
D. Yes, it is 60% This is the contractor's incorrect statement. The calculation based on official EVM formulas demonstrates that the actual progress is 52.5%, making the 60% claim verifiably false. ---
1. AACE International, Skills & Knowledge of Cost Engineering, 6th Edition. Morgantown, WV: AACE International, 2015.
Section 7.4.4, "Earned Value Analysis." This section explicitly defines the formula for Percent Complete (PC) as PC = EV / BAC. Applying this formula to the question's data (EV=105,000, BAC=200,000) yields 52.5%.
2. AACE International, Recommended Practice No. 10S-90, Cost Engineering Terminology. Morgantown, WV: AACE International, June 29, 2018.
Page 43, Definition of "Earned Value (EV)". Defines EV as "The value of the work completed to date. EV = % complete x BAC." This formula can be algebraically rearranged to % Complete = EV / BAC, confirming the calculation method.
Page 83, Definition of "Percent Complete". Defines it as "An estimate, expressed as a percent, of the amount of work that has been completed..." The EVM framework provides the objective method for this estimation.
3. Fleming, Q. W., & Koppelman, J. M. (2010). Earned Value Project Management (4th ed.). Project Management Institute.
Chapter 4, "The Five Core Data Elements," Page 29. This chapter details the fundamental EVM metrics. It explicitly states the formula for Performance Percent Complete as BAC% Complete = EV / BAC, which directly supports the correct answer.
Keep practicing
Take the free CCP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCP practice questions
- Question 1A used concrete pumping truck can be purchased for $125,000. The operation costs are expe…
- Question 3Which of the following best describes the concept of total cost management:
- Question 4What is a basic element of work or a task that must be performed over a given period of t…
- Question 5The goal of listening is to:
- Question 7When a person hears the words being said to him/her, but does not receive the message of …
- Question 8AACE International defines _____________as a technique of economic evaluation that sums o…