CCP practice question 21 of 25
After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is…
Choose your answer, then check it against the explanation.
After collecting the control information on a light rail project within an original budget of 200.0OO
work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and
110.000 work hours paid. The stated progress by the contractor is 60%.
After collecting the control information on a light rail project within an original budget of
200.000work hours, the construction contractor is ready for their monthly progress meeting with the
client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and
110.000 work hours paid. The stated progress by the contractor Is 60%.
Is the percent complete stated by the contractor correct?
Question 21 of 25
Keep practicing
Take the free CCP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCP practice questions
- Question 1A used concrete pumping truck can be purchased for $125,000. The operation costs are expe…
- Question 3Which of the following best describes the concept of total cost management:
- Question 4What is a basic element of work or a task that must be performed over a given period of t…
- Question 5The goal of listening is to:
- Question 7When a person hears the words being said to him/her, but does not receive the message of …
- Question 8AACE International defines _____________as a technique of economic evaluation that sums o…