CCP practice question 20 of 25
After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is…
Full set: 189 questionsThe Cost Performance Index (CPI) is a key metric in Earned Value Management (EVM) that measures the cost efficiency of the work accomplished. It is calculated as the ratio of the Budgeted Cost of Work Performed (BCWP), also known as Earned Value (EV), to the Actual Cost of Work Performed (ACWP), also known as Actual Cost (AC). Using the data provided: BCWP (earned) = 105,000 work hours ACWP (paid) = 110,000 work hours The formula is: CPI = BCWP / ACWP CPI = 105,000 / 110,000 = 0.9545, which rounds to 0.95. A CPI less than 1.0 indicates a cost overrun, meaning the project is costing more than planned for the work completed.
B. This option incorrectly inverts the standard CPI formula, calculating ACWP/BCWP. This ratio does not represent the standard Cost Performance Index.
C. This option incorrectly uses the Budgeted Cost for Work Scheduled (BCWS) instead of BCWP in the numerator, which does not measure performance against work actually completed.
D. This option is the inverse of the incorrect formula in option C. It uses BCWS instead of BCWP and inverts the standard ratio.
1. AACE International, Recommended Practice No. 10S-90, "Cost Engineering Terminology" (June 28, 2019).
Page 31: Defines Cost Performance Index (CPI) as "A measure of cost efficiency on a project. It is the ratio of earned value (EV) to actual cost (AC). CPI = EV/AC." The document equates EV with BCWP and AC with ACWP.
2. AACE International, Skills & Knowledge of Cost Engineering, 6th ed. (Morgantown, WV: AACE International, 2015).
Chapter 7, Section 7.3, "Progress and Cost Control": This section details the fundamentals of Earned Value Management, explicitly stating the formula for the Cost Performance Index as CPI = BCWP / ACWP. It explains that this index measures the value of work accomplished for every unit of cost incurred.
3. Humphreys, K. K., Project and Cost Engineers' Handbook, 4th ed. (New York: Marcel Dekker, 2005), sponsored by AACE International.
Chapter 11, "Cost Control," Page 268: The text provides the formula for cost performance: "Cost Performance Index (CPI) = BCWP/ACWP." It further explains that a value less than 1.0 indicates that costs are higher than budgeted.
Keep practicing
Take the free CCP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCP practice questions
- Question 1A used concrete pumping truck can be purchased for $125,000. The operation costs are expe…
- Question 3Which of the following best describes the concept of total cost management:
- Question 4What is a basic element of work or a task that must be performed over a given period of t…
- Question 5The goal of listening is to:
- Question 7When a person hears the words being said to him/her, but does not receive the message of …
- Question 8AACE International defines _____________as a technique of economic evaluation that sums o…