CCP practice question 20 of 25

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is…

Choose your answer, then check it against the explanation.

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client. A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%. What is the cost performance index (CPI)?