There are many implications for an organisation when using PRINCE 2 for managing projects. Which of the following statements are correct?
Full set: 210 questionsPRINCE2 is a process-based method that must be applied within its defined seven-process framework. It demands a controlled environment where every activity remains inside the authorised business case, objectives and scope. Consequently, the Project Manager follows the prescribed processes, staff work under tight control, and all actions must stay within agreed limits.
A. PRINCE2 gives the PM authority only within tolerances; major decisions must be escalated to the Project Board.
C. PRINCE2 specifies seven mandatory processes, so “all six processes” is factually wrong.
1. AXELOS. Managing Successful Projects with PRINCE2, 6th ed., 2017, §§4.1-4.4, pp. 19-25.
2. Ibid., Principle “Manage by Stages & Exception”, §7.3, p. 77.
3. Ibid., Role description, Project Board, §12.2, p. 161.
Keep practicing
Take the free CIMAPRA19-E02-1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CIMAPRA19-E02-1 practice questions
- Question 1According to the Project Management Body of Knowledge as outlined by the Project Manageme…
- Question 2H is the owner of a motorcycle dealership in Los Angeles which provides sales, repair and…
- Question 3V is the owner of a small jewellery business which deals exclusively in pearls. The busin…
- Question 4Identify ways in which an orgnisation can undertake qualitative research. Select ALL that…
- Question 5The concept of core competences is key to successful outsourcing strategy. Organisations …
- Question 6X is a manufacturing company that has achieved long term success by understanding the str…