There are many implications for an organisation when using PRINCE 2 for managing projects. Which of the following statements are correct?

Full set: 210 questions
Answer options
A: The Project Manager can make decisions independently without the approval of the board
B: The Project Manager must follow a restricted step by step procedure Correct answer
C: All six processes and the many sub processes must be followed
D: Project staff must operate under a strictly managed and controlled regime Correct answer
E: All actions must be within the bounds of agreed project objectives and scope Correct answer
Correct Answer:
B. The Project Manager must follow a restricted step by step procedure; D. Project staff must operate under a strictly managed and controlled regime; E. All actions must be within the bounds of agreed project objectives and scope
Explanation

PRINCE2 is a process-based method that must be applied within its defined seven-process framework. It demands a controlled environment where every activity remains inside the authorised business case, objectives and scope. Consequently, the Project Manager follows the prescribed processes, staff work under tight control, and all actions must stay within agreed limits.

Why Incorrect

A. PRINCE2 gives the PM authority only within tolerances; major decisions must be escalated to the Project Board.
C. PRINCE2 specifies seven mandatory processes, so “all six processes” is factually wrong.

References

1. AXELOS. Managing Successful Projects with PRINCE2, 6th ed., 2017, §§4.1-4.4, pp. 19-25.

2. Ibid., Principle “Manage by Stages & Exception”, §7.3, p. 77.

3. Ibid., Role description, Project Board, §12.2, p. 161.