CIS-PPM practice question 5 of 15
How is a resource group’s capacity derived for resource planning?
Full set: 60 questionsA resource group's capacity is not a static, stored value. Instead, it is dynamically calculated by the system. The capacity is the sum of the capacities of all individual members belonging to that group. Each member's capacity is determined by their assigned schedule (FTE). Therefore, the group's total capacity is the aggregate of what its constituent members can provide, reflecting the collective workforce potential for planning purposes.
B. Stored in ResourceAggregateDaily table: This table stores pre-calculated aggregate data for reporting performance, but the capacity is derived from members, not sourced from this table.
C. Stored with Group Record: The group record (sysusergroup) itself does not have a field to store a calculated capacity; it is determined dynamically based on its members.
D. Stored in ResourceAllocationDaily table: This table stores daily allocation records for individual resources against specific tasks, not the overall capacity of a group.
1. ServiceNow Product Documentation, "Create a resource group". The documentation states, "A group's capacity is the sum of the capacities of the group members."
2. ServiceNow Product Documentation, "Resource management schedules". This document explains that individual capacity is based on schedules, and group capacity is an aggregation of these individuals.
Keep practicing
Take the free CIS-PPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CIS-PPM practice questions
- Question 1In what way would you restrict the assigned to field on a project task to only allow user…
- Question 2Which of the following checks to see if the assessable record exists for the demand and c…
- Question 4To use the Time Sheet dashboard, what plugin must be installed?
- Question 6In order for a business unit to have its own Idea Portal to retrieve data, what must be c…
- Question 7The PPM Standard plugin enables an it_project_manager to perform the following activities…
- Question 8A customer requires five (5) teamspaces to support different departments. What should you…