CIS-PPM practice question 8 of 15
A customer requires five (5) teamspaces to support different departments. What should you do?
Full set: 60 questionsTeamspaces in ServiceNow PPM are modular and activated individually based on need. Each teamspace, such as for Agile, Project, or Demand, is enabled by activating its specific plugin. This allows an organization to tailor the PPM environment by only enabling the functional areas required by different departments.
A. A property might configure an already active teamspace, but it does not enable the core functionality of the teamspace itself.
B. Contacting an Account Representative is for licensing paid applications, not for activating standard, entitled features like teamspaces.
D. UI Policies and Business Rules are used for controlling form behavior and business logic, not for activating entire application modules like teamspaces.
1. ServiceNow Product Documentation, "Teamspaces for PPM", Rome. "Activate the plugins for the teamspaces that you want to use in your instance. For example, to use the Agile teamspace, activate the Agile - Teamspace (com.snc.sdlc.agile.teamspace) plugin."
2. ServiceNow Product Documentation, "Components installed with Project Portfolio Management", Rome. This document lists the various plugins associated with PPM, including individual teamspace plugins like "Project - Teamspace" (com.snc.project.teamspace).
Keep practicing
Take the free CIS-PPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CIS-PPM practice questions
- Question 1In what way would you restrict the assigned to field on a project task to only allow user…
- Question 2Which of the following checks to see if the assessable record exists for the demand and c…
- Question 4To use the Time Sheet dashboard, what plugin must be installed?
- Question 5How is a resource group’s capacity derived for resource planning?
- Question 6In order for a business unit to have its own Idea Portal to retrieve data, what must be c…
- Question 7The PPM Standard plugin enables an it_project_manager to perform the following activities…