MSP-FOUNDATION practice question 13 of 25
Which factor often results in an organization choosing to manage a change investment as a programme?
Full set: 117 questionsA programme is the appropriate management framework when an organization needs to implement complex, transformational change to achieve strategic objectives. Unlike projects, which deliver outputs, programmes deliver outcomes and benefits that often require fundamental shifts in an organization's culture and established ways of working. This need to manage the human and operational aspects of change, alongside the delivery of new capabilities from projects, is a primary reason for adopting a programme management approach.
A. The governance applied to ensure that the organization's individual investments offer strategic value is a primary function of portfolio management, which operates at a higher level than a single programme.
C. The need to comply with organizational standards for risk management is a requirement for all initiatives, including individual projects and business-as-usual activities, not a specific driver for choosing a programme structure.
D. While programmes often involve many stakeholders, a large number of stakeholders can also be a feature of a complex project. It is a characteristic, but not the fundamental reason for choosing a programme.
1. AXELOS, "Managing Successful Programmes (MSP) 5th Edition" (2020).
Section 1.3, 'When to use a programme', Page 6: "A programme is the appropriate framework when the change requires the coordinated delivery of multiple projects and other work to make a measurable improvement in the business... This is particularly true when there is a need for a significant change to an organization's culture and ways of working." This directly supports the correct answer (B).
Section 1.4, 'Programmes, portfolios, and projects', Page 7: This section clarifies that portfolio management is concerned with "doing the right programmes and projects," which aligns with the reasoning for why option A is incorrect.
Chapter 4, 'MSP governance themes': This chapter details universal requirements like risk management (p. 48) and stakeholder engagement (p. 42), confirming they are integral parts of management but not the primary reason to choose a programme over a project, thus invalidating options C and D as the core driver.
Keep practicing
Take the free MSP-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other MSP-FOUNDATION practice questions
- Question 1Which is a COMMON reason for organizations to invest in programmes of change?
- Question 2Which activity contributes MOST to achieving the ‘align with priorities’ principle?
- Question 3Which activity contributes MOST to achieving the ‘bring pace and value’ principle?
- Question 4Which process checks that a programme is worth the time and resources needed to plan the …
- Question 5Which role/group is responsible for implementing the programme strategy?
- Question 6Which document is MOST LIKELY to describe the required levels of privacy?