After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in which you document these changes?
Full set: 490 questionsWhen a strategic change occurs, the attributes of the portfolio components (e.g., budget, schedule, scope, strategic alignment) may be altered. These changes to the state and characteristics of the components are documented as "Portfolio updates." This output reflects the current status and composition of the portfolio. The Portfolio Management Plan describes how to manage, while the Portfolio Strategic Plan sets direction; neither is the repository for the current attributes of individual components.
A. Portfolio Strategic Plan updates: This plan contains high-level strategic goals and objectives, not the detailed, operational attributes of individual components.
C. Portfolio Management Plan updates: This plan details the processes and procedures for managing the portfolio, not the real-time data or status of its components.
D. Portfolio Process Assets updates: These are templates, lessons learned, and organizational knowledge bases, not the live data reflecting the current state of portfolio components.
1. Project Management Institute. (2013). The Standard for Portfolio Management (3rd ed.). Section 3.4, Manage Strategic Change, p. 41. (Figure 3-1 explicitly lists "Portfolio updates" as an output of this process).
2. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 3.0, Portfolio Management Process Groups, p. 26. (Figure 3-1 shows that Executing processes produce updates to the portfolio itself).
3. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Glossary, p. 142. (Defines Portfolio as "Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives." Updates to this are updates to the components).
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …