For years, your aerospace company has been a leader in the development of sophisticated avionic hardware systems around the world. The executives…
Full set: 490 questionsTo assess internal resource capacity and identify skill set limitations for a new strategic direction, the most effective method is to perform a competency analysis. This involves first identifying the specific competencies (skills, knowledge, and behaviors) required for the new software-focused initiatives. Next, competency profiles are developed for the existing internal staff to document their current skills. By comparing the required competencies with the existing profiles, the organization can precisely identify skill gaps. This structured approach provides the necessary data to plan for training, hiring, or sourcing externally to meet the new strategic needs.
B. Interest is not a substitute for competency, and past performance evaluations may not reflect skills needed for a new, different product line.
C. Reviewing education and training is a partial measure; it does not confirm actual on-the-job competency or experience level.
D. Issuing a Request for Information (RFI) is a step to explore external options, not to assess internal capacity, which is the specific task.
1. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 5.2.2.2, Resource Capacity Analysis, p. 72. This section describes analyzing current resource capacity against future demand, which inherently involves assessing skills and competencies.
2. Collings, D. G., & Mellahi, K. (2009). Strategic talent management: A review and research agenda. Human Resource Management Review, 19(4), 304-313. https://doi.org/10.1016/j.hrmr.2009.04.001. This academic article discusses the importance of identifying key competencies and assessing the internal talent pool to align with strategic goals.
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …
- Question 7A portfolio manager needs to continuously balance the need and requirements with the avai…