PFMP practice question 5 of 35
You have scored the portfolio components and are analyzing the data in order to prioritize the components. Using the following scoring table, which…
Full set: 490 questionsThis question requires selecting the optimal set of components that maximizes value (score) without exceeding the budget constraint of 40k USD. First, options A, B, and C must be eliminated as their total costs (52k, 55k, and 49k respectively) all exceed the 40k budget. Option D, consisting of components D, B, and E, has a total cost of 13k + 15k + 11k = 39k, which is within the budget. Therefore, it is the only feasible option presented. This selection process is a core activity within the "Optimize Portfolio" process, where components are chosen based on their value and alignment with constraints like available funding.
A. The total cost of components A, C, E, and B is 52k USD, which is over the 40k USD budget and is therefore not a valid selection.
B. The total cost of components D, B, C, and E is 55k USD, which is over the 40k USD budget and is therefore not a valid selection.
C. The total cost of components D, B, E, and A is 49k USD, which is over the 40k USD budget and is therefore not a valid selection.
1. Project Management Institute. (2018). The Standard for Portfolio Management – Fourth Edition. Newtown Square, PA: Project Management Institute. Section 6.3, "Optimize Portfolio," pp. 79-83.
2. Archer, N. P., & Ghasemzadeh, F. (1999). An integrated framework for project portfolio selection. International Journal of Project Management, 17(4), 207-216. (This paper discusses the use of scoring models and resource constraints, like budget, as fundamental to the portfolio selection process). https://doi.org/10.1016/S0263-7863(98)00032-5
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …
- Question 7A portfolio manager needs to continuously balance the need and requirements with the avai…