PFMP practice question 35 of 35

Assume you are working to prepare the low-level schedule and timelines for portfolio components. You want to make sure, as the portfolio manager, for your country's initiatives to promote an awareness of the importance of climate change, that each component then can be monitored and tracked to assess performance. To do so, you should:

Full set: 490 questions
Answer options
A: Set up KPIs for each component that are consistent for ease of measurement
B: Determine the critical success factors at the portfolio level and then ensure each component contributes toward their realization
C: Review the portfolio roadmap Correct answer
D: Review the portfolio performance plan
Correct Answer:
C. Review the portfolio roadmap
Explanation

The portfolio roadmap is a high-level, strategic artifact that provides a timeline for portfolio components, showing their sequencing and dependencies in relation to strategic objectives. To prepare low-level schedules and timelines for individual components, the portfolio manager must first consult this roadmap. It serves as the primary input and guide, ensuring that the detailed component schedules are aligned with the overall strategic plan and timeline established at the portfolio level. This alignment is crucial for effective monitoring and performance tracking against the portfolio's strategic goals.

Why Incorrect

A. Setting up KPIs is part of performance management planning and execution, which follows scheduling, not a prerequisite for creating the schedule itself.
B. Determining critical success factors is a strategic planning activity that occurs much earlier and informs the creation of the roadmap, not the detailed scheduling.
D. The portfolio performance plan outlines how performance will be measured (metrics, KPIs), not the schedule of work to be performed.

References

1. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 3.2.2, Plan Portfolio Management, p. 57. The portfolio roadmap is listed as a key output, described as a "high-level timeline of portfolio components."

2. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Figure 3-5, Portfolio Management Process Groups and Processes, p. 48. The portfolio roadmap is an output of Planning and an input to Authorize and Govern processes, indicating its role in guiding execution.