PMI-RMP practice question 35 of 35
A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier. What should the risk manager do in this scenario?
Full set: 264 questionsSenior management's request to remove contingency reserves to accelerate the schedule indicates a potential misunderstanding of the purpose of these reserves. Contingency reserves are allocated to manage the time or cost impact of identified risks (the "known-unknowns"), not to pad the schedule. Removing them arbitrarily increases the project's vulnerability to threats without a corresponding reduction in risk exposure. The most appropriate action is to facilitate a collaborative session with senior management and other key stakeholders. A risk planning workshop allows the risk manager to explain the risk analysis, the rationale behind the reserves, and align on an acceptable level of risk exposure, ensuring any decision is made with a full understanding of its consequences.
A. Reviewing project schedule estimates does not address the core issue, which is a strategic disagreement with management about risk appetite and the function of reserves.
B. Changing the response strategies without a proper re-evaluation and stakeholder consensus, simply to accommodate a request, is a reactive and unsound risk management practice.
C. Reducing the contingency reserves without a formal risk reassessment and stakeholder agreement would be an irresponsible dereliction of the risk manager's duty to protect the project.
1. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Newtown Square, PA: Project Management Institute. Section 4.3.3.2, "Meetings and Facilitation," highlights the use of meetings and workshops to develop the risk management plan, define risk thresholds, and achieve stakeholder consensus on the overall risk strategy.
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Newtown Square, PA: Project Management Institute. Section 11.1.2.3, "Meetings," states that project teams may hold planning meetings to develop the risk management plan, and a key outcome is ensuring stakeholders are aligned on the plan for managing risk.
3. de Meyer, A., Loch, C. H., & Pich, M. T. (2002). Managing Project Uncertainty: From Variation to Chaos. MIT Sloan Management Review, 43(2), 60–67. This article emphasizes that managing uncertainty requires clear communication and a shared understanding among stakeholders, which is best achieved through collaborative sessions rather than unilateral decisions. A workshop is a primary tool for creating this shared context.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…