PMI-RMP practice question 34 of 35

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing…

Choose your answer, then check it against the explanation.

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost. What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?
Answer options
Question 34 of 35

Keep practicing

Take the free PMI-RMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-RMP practice questions

Scroll to Top