PMI-RMP practice question 34 of 35

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost. What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

Full set: 264 questions
Answer options
A: Reinforce to the stakeholders that the risk identification was done properly during the last sprint.
B: Highlight the importance of agreeing on the risk identification to avoid further delays.
C: Conduct a separate meeting to show the risk identification analysis to the stakeholders.
D: Ensure that the most knowledgeable members of the team validate risk identification processes. Correct answer
Correct Answer:
D. Ensure that the most knowledgeable members of the team validate risk identification processes.
Explanation

The central issue is a lack of agreement and trust in the risk identification from the sponsor and team members. The most effective way to resolve these concerns is to build credibility and consensus. By having the most knowledgeable team members—Subject Matter Experts (SMEs)—validate the risk identification process and its findings, the risk manager leverages expert judgment. This approach provides an authoritative, team-based confirmation of the risks, which is more persuasive than the risk manager's analysis alone. It directly addresses the stakeholders' skepticism and facilitates buy-in for the subsequent risk response planning.

Why Incorrect

A. Reinforcing that the process was done properly is an assertive, not a collaborative, approach and fails to address the stakeholders' specific doubts with evidence or consensus.
B. Highlighting the importance of agreement to avoid delays is a pressure tactic that does not resolve the underlying disagreement about the validity of the identified risks.
C. While showing the analysis is a positive step towards transparency, it may be insufficient if the stakeholders question the risk manager's judgment or assumptions. Validation by experts is a more powerful resolution.

References

1. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.

Section 6.3.2.1 Expert Judgment: This section emphasizes that expertise from individuals with specialized knowledge should be used throughout the risk management process, including risk identification. When disagreement arises, leveraging these experts to validate the findings is a standard practice to build consensus and ensure accuracy.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition.

Section 2.4, Planning Performance Domain: This domain states, "Planning activities are undertaken with the project team and other stakeholders to develop the approach and plans for the project work." This principle supports a collaborative approach. When stakeholders disagree, the solution involves further engagement and leveraging team expertise, as suggested in option D, rather than unilateral declarations.

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley.

Chapter 19, Risk Management: This chapter discusses that effective risk identification is a team effort, not the sole responsibility of one person. It highlights the use of techniques like brainstorming and expert interviews, underscoring the value of involving knowledgeable team members to ensure risks are properly identified and validated, which is crucial for gaining stakeholder acceptance.