PMI-RMP practice question 34 of 35
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing…
Choose your answer, then check it against the explanation.
During the weekly project meeting a risk manager identified new risks in the last sprint, which might
impact the project cost by implementing mitigation plans. The sponsor and some project team
members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members' concerns about
risk identification?
Question 34 of 35
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 3A project lihat was in the execution phase for the last six months was put on hold and wa…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6A risk management professional is currently facilitating the risk planning process with t…
