PMI-RMP practice question 32 of 35
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis…
Full set: 264 questionsThe core problem is that planned risk responses were not executed. The most effective way to ensure planned actions are carried out is to integrate them into the formal project plan. By adding the risk response actions as specific tasks in the project schedule, they become part of the project's work breakdown structure (WBS) and activity list. This makes the tasks visible, assigns clear ownership, and allows them to be tracked, managed, and controlled just like any other project activity. This direct integration into the project's execution framework is the standard and most effective method to prevent such implementation failures.
A. This assumes the risk owners lacked the necessary skills, but the scenario suggests a failure of execution, not a lack of capability.
B. Risk triggers and thresholds are used to determine when a response is needed, not to ensure the planned response is actually implemented.
C. While communication is important, it is a less direct and less reliable mechanism for ensuring task completion than formally scheduling and tracking the work.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.).
Section 11.6 Implement Risk Responses: This process is focused on executing agreed-upon risk response plans.
Section 11.6.3.1 Project Management Plan Updates: The guide explicitly states, "The project schedule is updated with the activities needed to implement the agreed-upon responses." This directly supports that risk response actions should be added to the schedule to ensure they are implemented.
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.
Section 5.7 Implement Risk Responses (p. 61): "To be effective, the implementation of agreed-upon risk responses needs to be integrated into the overall management of the project. The project manager ensures that the agreed-upon risk responses are included in the project management plan, and that the risk owners are prepared to take action." Adding tasks to the schedule is a primary method of this integration.
3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd.
Chapter 10: Risk Response Planning: Hillson emphasizes that for risk responses to be effective, they must be converted into actions. He states, "Each selected response must be developed into a set of actions to be included in the project plan... Responsibility for each action must be allocated to a specific individual." This reinforces the principle of embedding response actions into the project plan and schedule.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…