PMI-RMP practice question 32 of 35

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis…

Full set: 264 questions
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented. What should the project manager have done to avoid this?
Answer options
A: Provided regular training to the risk owners for plan implementation
B: Determined risk triggers and thresholds in the risk response plan
C: Increased communications to influence stakeholder risk responses
D: Updated the project schedule, adding risk owner implementation tasks. Correct answer
Correct Answer:
D. Updated the project schedule, adding risk owner implementation tasks.
Explanation

The core problem is that planned risk responses were not executed. The most effective way to ensure planned actions are carried out is to integrate them into the formal project plan. By adding the risk response actions as specific tasks in the project schedule, they become part of the project's work breakdown structure (WBS) and activity list. This makes the tasks visible, assigns clear ownership, and allows them to be tracked, managed, and controlled just like any other project activity. This direct integration into the project's execution framework is the standard and most effective method to prevent such implementation failures.

Why Incorrect

A. This assumes the risk owners lacked the necessary skills, but the scenario suggests a failure of execution, not a lack of capability.
B. Risk triggers and thresholds are used to determine when a response is needed, not to ensure the planned response is actually implemented.
C. While communication is important, it is a less direct and less reliable mechanism for ensuring task completion than formally scheduling and tracking the work.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.).

Section 11.6 Implement Risk Responses: This process is focused on executing agreed-upon risk response plans.

Section 11.6.3.1 Project Management Plan Updates: The guide explicitly states, "The project schedule is updated with the activities needed to implement the agreed-upon responses." This directly supports that risk response actions should be added to the schedule to ensure they are implemented.

2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.

Section 5.7 Implement Risk Responses (p. 61): "To be effective, the implementation of agreed-upon risk responses needs to be integrated into the overall management of the project. The project manager ensures that the agreed-upon risk responses are included in the project management plan, and that the risk owners are prepared to take action." Adding tasks to the schedule is a primary method of this integration.

3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd.

Chapter 10: Risk Response Planning: Hillson emphasizes that for risk responses to be effective, they must be converted into actions. He states, "Each selected response must be developed into a set of actions to be included in the project plan... Responsibility for each action must be allocated to a specific individual." This reinforces the principle of embedding response actions into the project plan and schedule.