PMI-RMP practice question 31 of 35
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique. Which technique should the risk manager use in this situation?
Full set: 264 questionsThe Delphi method is a structured communication technique designed to achieve consensus among a panel of experts. It uses a series of anonymous questionnaires, interspersed with controlled feedback. A facilitator summarizes the experts' anonymous responses from each round and shares the summary with the group. This iterative process allows experts to revise their earlier opinions based on the collective feedback without the influence of dominant personalities or direct confrontation. This makes it the most suitable technique for resolving disagreements and building consensus when experts initially fail to agree on risks and their characteristics.
A. Brainstorming: This technique is primarily for generating a wide range of ideas and is often the first step in a workshop, not a method for resolving subsequent disagreements.
C. Focus group: This is a qualitative data-gathering technique to explore perceptions and attitudes, not a structured process designed to force a consensus among disagreeing technical experts.
D. Checklist analysis: This method uses historical data from previous projects to ensure common risks are not overlooked; it does not facilitate consensus on new or disputed risks.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.2.2.2 Data Gathering. Newtown Square, PA: Project Management Institute. The guide describes the Delphi technique as a method where "a consensus of experts...can be reached" through anonymous, iterative questionnaires facilitated to prevent bias and undue influence.
2. Project Management Institute. (2009). Practice Standard for Project Risk Management. Section 4.2.2.2 Information-Gathering Techniques. Newtown Square, PA: Project Management Institute. This standard explicitly states the Delphi Technique is used to "reduce bias in the data and keeps any one person from having undue influence on the outcome," which is critical when experts disagree.
3. Okoli, C., & Pawlowski, S. D. (2004). The Delphi method as a research tool: an example, design considerations and applications. Information & Management, 42(1), 15–29. This paper details the characteristics of the Delphi method, including anonymity, iteration, and controlled feedback, as a formal process for achieving convergence of opinion and consensus (p. 19). https://doi.org/10.1016/j.im.2003.11.002
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…