PMI-RMP practice question 30 of 35
An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain. What should the risk management team leader do in the early stages of the project?
Full set: 264 questionsIn the early stages of a project, the primary responsibility of the risk management leader is to establish the framework for how risk will be managed. This corresponds to the "Plan Risk Management" process. A critical success factor, especially in a complex, multinational project, is ensuring all stakeholders share a common understanding of the risk management processes, terminology, their roles, and responsibilities. Educating stakeholders on best practices is a foundational activity that fosters a proactive risk culture, ensures buy-in, and facilitates effective participation in subsequent risk management activities like identification and analysis. This alignment is essential before executing specific risk tasks.
A. Qualitative risk analysis is a subsequent step that occurs only after the risk management plan has been established and risks have been identified.
B. Planning risk responses is performed after risks have been identified and analyzed (qualitatively and/or quantitatively), not during the initial project stages.
D. Benchmarking is a useful technique for gathering data or identifying potential risks, but establishing the internal framework and educating stakeholders is a more fundamental, primary duty for the leader.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Newtown Square, PA: Project Management Institute.
Section 11.1, Plan Risk Management: This process is about defining how to conduct risk management activities. A key part of this is ensuring all participants understand the approach. The output, the Risk Management Plan (Section 11.1.3.1), defines roles and responsibilities, which requires communication and education to be effective.
2. PMI. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Newtown Square, PA: Project Management Institute.
Section 4.2, Develop Risk Management Plan: This section emphasizes that the plan is developed to ensure risk management is appropriate for the project and the organization. It states, "The risk management plan may also include protocols for communication, consultation, and reporting for risk management activities," which directly supports the need for stakeholder education and alignment.
3. Hillson, D. (2002). The risk breakdown structure (RBS) as an aid to effective risk management. Proceedings of the 5th European Project Management Conference.
This paper, while focused on the RBS, emphasizes that a fundamental step in implementing a risk management process is to "establish a common understanding and language for risk," which is achieved through training and communication with stakeholders. This aligns directly with educating stakeholders on best practices.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…