PMI-RMP practice question 29 of 35

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues…

Choose your answer, then check it against the explanation.

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected. What should the risk manager do first?
Answer options
Question 29 of 35

Keep practicing

Take the free PMI-RMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-RMP practice questions

Scroll to Top