PMI-RMP practice question 29 of 35
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected. What should the risk manager do first?
Full set: 264 questionsThe addition of "extra days" to activities is a form of informal risk handling known as padding, which is discouraged in formal project management. The stakeholders' request to remove this padding necessitates a structured approach to managing schedule uncertainty. The risk manager's first responsibility is to ensure that risks are properly addressed. Therefore, the initial step is to review the formal risk response plan. This review will validate if the identified risks (which the padding was meant to cover) have appropriate, planned responses. Based on this review, a formal schedule contingency reserve can be calculated and justified to stakeholders, allowing the improper activity padding to be removed without exposing the project to unmanaged risk.
A. Remove the activity padding: This is a premature action that addresses the symptom (longer schedule) but ignores the underlying risks, potentially leaving the project vulnerable.
C. Update the risk contingency plan: Updating is a subsequent step. The first action is to review the existing plan to determine if and how it needs to be updated.
D. Update the schedule constraints: This is an outcome of a successful risk management process, not the first step. The schedule can only be changed after risks have been properly analyzed and addressed.
1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Project Management Institute.
Section 2.7.3, Uncertainty: This section discusses dealing with uncertainty, ambiguity, and complexity. It states, "Risk is addressed with several approaches. One approach is to build a contingency reserve into the schedule and budget." This highlights the formal method (contingency reserve) that should replace informal padding. The review of the risk response plan is the first step to establishing this formal reserve.
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Project Management Institute.
Section 5.6, Plan Risk Responses: This section details the process of developing options and actions to enhance opportunities and reduce threats. The scenario describes an unplanned response (padding). The correct action is to formally review and plan responses. The standard notes, "The Plan Risk Responses process ensures that identified risks are properly addressed." Reviewing the plan is the first step in this assurance.
3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd.
Chapter 10, Risk Response Planning: This chapter distinguishes between padding individual estimates and creating a managed contingency reserve. It emphasizes that contingency should be based on a rational assessment of risk exposure. The first step to move from padding to a proper reserve is to review the existing risk analysis and response strategies.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…