PMI-RMP practice question 28 of 35
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key. What should the project manager do next?
Full set: 264 questionsThe emergence of multiple new risks indicates that the initial risk identification was insufficient or that the project environment has changed. Project risk management is not a one-time activity performed only at the beginning of a project. The Project Management Institute (PMI) standards emphasize that risk management processes, particularly risk identification, are iterative and must be performed continuously throughout the project lifecycle. By applying an iterative approach, the project manager ensures that the team regularly scans for and identifies new risks, addressing the fundamental process gap highlighted in the scenario.
A. Reviewing assumptions and constraints around risks is a specific technique for identifying risks, but applying an iterative approach is the overarching process improvement required.
B. Developing the risk response plans for identified risks is a subsequent step that occurs only after the new risks have been analyzed and prioritized.
C. Determining the likelihood and impact of the risks (Qualitative Risk Analysis) is the step that follows formal identification and logging of the risks in the register.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.2, Identify Risks. The guide states, "Identify Risks is an iterative process, because new risks may emerge as the project progresses through its life cycle." (p. 411).
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Section 4.3.2, Identify Risks: Inputs, Tools and Techniques, and Outputs. This standard emphasizes, "Risk identification is performed throughout the duration of the portfolio, program, or project... The iterative nature of risk identification is universal..." (p. 49).
3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd. Chapter 5 discusses the importance of a continuous and iterative risk process, stating that risk identification should be a "rolling activity" rather than a single event. (p. 87).
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…
