PMI-RMP practice question 27 of 35

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and…

Full set: 264 questions
The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends. How should the project manager and the risk manager handle this situation?
Answer options
A: Ensure the project complies with the current traffic regulations and laws.
B: Send a letter to the traffic authority with the general project information.
C: Perform inquiries on the website of the traffic authority weekly.
D: Meet with the traffic authority staff in charge of the new regulation. Correct answer
Correct Answer:
D. Meet with the traffic authority staff in charge of the new regulation.
Explanation

The identified situation represents a significant external risk related to regulatory compliance. The most effective and proactive approach to managing such a risk is through direct stakeholder engagement. Meeting with the traffic authority staff responsible for the new regulation allows the project team to gather firsthand, accurate information about the potential changes, their scope, likelihood, and timeline. This direct communication is a key information-gathering technique that enables a more precise risk analysis and the development of appropriate response strategies, thereby reducing uncertainty and its potential negative impact on the project.

Why Incorrect

A. This is a baseline requirement, not a risk management action for a future event. It fails to address the uncertainty of the new regulations.
B. This is a passive, one-way communication method that is unlikely to yield the detailed insights required for effective risk planning.
C. This is a passive monitoring technique. Information on a public website may be delayed, incomplete, or lack the necessary context for decision-making.

References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). In the Stakeholder Performance Domain, it is stated, "Effective stakeholder engagement includes implementing strategies and actions to promote productive involvement of stakeholders in project decision making and execution... Engaging stakeholders proactively and effectively can mean the difference between project success and failure." (Section 2.7, p. 66). Meeting with the authority is a direct application of this principle.

2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. The "Identify Risks" process lists "Interviews" as a key information-gathering technique. The standard explains, "Interviews with project participants, stakeholders, and subject matter experts can identify risks." (Section 4.4.2.2, p. 51). The traffic authority staff are the primary subject matter experts for this specific risk.

3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd. This text emphasizes that for external risks, particularly political or regulatory ones, proactive engagement is crucial. "It is essential to understand the stakeholder's position, and this can often only be achieved through direct dialogue." (Paraphrased from concepts in Chapter 5: Identifying Risks).