PMI-RMP practice question 27 of 35
The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and…
Full set: 264 questionsThe identified situation represents a significant external risk related to regulatory compliance. The most effective and proactive approach to managing such a risk is through direct stakeholder engagement. Meeting with the traffic authority staff responsible for the new regulation allows the project team to gather firsthand, accurate information about the potential changes, their scope, likelihood, and timeline. This direct communication is a key information-gathering technique that enables a more precise risk analysis and the development of appropriate response strategies, thereby reducing uncertainty and its potential negative impact on the project.
A. This is a baseline requirement, not a risk management action for a future event. It fails to address the uncertainty of the new regulations.
B. This is a passive, one-way communication method that is unlikely to yield the detailed insights required for effective risk planning.
C. This is a passive monitoring technique. Information on a public website may be delayed, incomplete, or lack the necessary context for decision-making.
1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). In the Stakeholder Performance Domain, it is stated, "Effective stakeholder engagement includes implementing strategies and actions to promote productive involvement of stakeholders in project decision making and execution... Engaging stakeholders proactively and effectively can mean the difference between project success and failure." (Section 2.7, p. 66). Meeting with the authority is a direct application of this principle.
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. The "Identify Risks" process lists "Interviews" as a key information-gathering technique. The standard explains, "Interviews with project participants, stakeholders, and subject matter experts can identify risks." (Section 4.4.2.2, p. 51). The traffic authority staff are the primary subject matter experts for this specific risk.
3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd. This text emphasizes that for external risks, particularly political or regulatory ones, proactive engagement is crucial. "It is essential to understand the stakeholder's position, and this can often only be achieved through direct dialogue." (Paraphrased from concepts in Chapter 5: Identifying Risks).
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…