As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
Full set: 264 questionsThe activity described, a risk response audit, is a tool and technique within the Monitor Risks process. The purpose of this audit is to evaluate the effectiveness of the risk management plan and the implemented risk responses. Once the audit is complete and the effectiveness has been verified, the immediate and logical next step is to formally document the findings and communicate them to relevant stakeholders as per the communications management plan. This ensures that all parties are aware of the outcomes, and the results can be incorporated into lessons learned and organizational process assets.
B. Running a workshop to analyze effectiveness would be a component of the audit itself, not a subsequent step after the audit is already completed.
C. A risk reserve analysis is an ongoing monitoring activity, but it is not the direct sequential action that follows the completion of a risk response audit.
D. Verifying that risk response actions have been documented is an integral part of conducting the audit, not an action taken after the audit is finished.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute.
Section 11.7.2.3 Audits: This section describes risk audits as a tool to "examine and document the effectiveness of risk responses... as well as the effectiveness of the risk management process."
Section 11.7.3.1 Work Performance Information: The outputs of the Monitor Risks process, which includes audits, generate work performance information. This information is then used to create work performance reports for distribution to stakeholders, directly supporting the action of communicating results.
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Project Management Institute.
Section 5.7 Monitor Risk (p. 57): This section states, "The results of risk monitoring are communicated to relevant stakeholders in accordance with the communications management plan." This confirms that communicating the results of monitoring activities, such as an audit, is a required step in the process.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…