PMI-RMP practice question 26 of 35

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Full set: 264 questions
Answer options
A: Close and communicate the results of the risk response actions. Correct answer
B: Run a workshop to analyze the effectiveness of the risk plan.
C: Conduct a risk reserve analysis and document the results.
D: Verify that all risk response actions have been documented.
Correct Answer:
A. Close and communicate the results of the risk response actions.
Explanation

The activity described, a risk response audit, is a tool and technique within the Monitor Risks process. The purpose of this audit is to evaluate the effectiveness of the risk management plan and the implemented risk responses. Once the audit is complete and the effectiveness has been verified, the immediate and logical next step is to formally document the findings and communicate them to relevant stakeholders as per the communications management plan. This ensures that all parties are aware of the outcomes, and the results can be incorporated into lessons learned and organizational process assets.

Why Incorrect

B. Running a workshop to analyze effectiveness would be a component of the audit itself, not a subsequent step after the audit is already completed.
C. A risk reserve analysis is an ongoing monitoring activity, but it is not the direct sequential action that follows the completion of a risk response audit.
D. Verifying that risk response actions have been documented is an integral part of conducting the audit, not an action taken after the audit is finished.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute.

Section 11.7.2.3 Audits: This section describes risk audits as a tool to "examine and document the effectiveness of risk responses... as well as the effectiveness of the risk management process."

Section 11.7.3.1 Work Performance Information: The outputs of the Monitor Risks process, which includes audits, generate work performance information. This information is then used to create work performance reports for distribution to stakeholders, directly supporting the action of communicating results.

2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Project Management Institute.

Section 5.7 Monitor Risk (p. 57): This section states, "The results of risk monitoring are communicated to relevant stakeholders in accordance with the communications management plan." This confirms that communicating the results of monitoring activities, such as an audit, is a required step in the process.