PMI-RMP practice question 25 of 35
A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?
Full set: 264 questionsProject risk management is an iterative and continuous process, not a one-time event. The Identify Risks process should be performed throughout the project's life cycle. While an initial identification is done early in planning, new risks can emerge, and existing risks can change as the project progresses. Therefore, the project manager must ensure the team is proactively and continuously identifying risks. This ongoing vigilance allows for timely analysis and the development of appropriate response strategies, which is a core principle of effective project risk management.
A. Identifying risks only at the project's midpoint is insufficient and reactive, as critical risks present from the start would be missed.
C. The assertion that a project's risk posture will not change is incorrect; risk is dynamic and evolves throughout the project life cycle.
D. Using separate risk registers creates information silos and prevents an integrated, project-level view of risk, hindering effective prioritization and response planning.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.2, Identify Risks. "Identify Risks is an iterative process, because new risks may emerge as the project progresses through its life cycle."
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Section 4.3, Identify Risks, p. 45. "The Identify Risks process is performed throughout the life cycle of the portfolio, program, or project. The frequency of iteration and the level of participation may vary depending on the situation."
3. Hillson, D. (2002). The Risk Breakdown Structure (RBS) as an Aid to Effective Risk Management. Project Management Institute Annual Seminars & Symposium. This paper, while focused on the RBS, reinforces the principle that risk identification is a structured and ongoing process, stating, "The aim of the risk identification process is to identify all knowable risks to the project..." which implies a continuous effort to uncover what becomes "knowable" over time.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…
