PMI-RMP practice question 24 of 35

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats. What should the risk manager do next?

Full set: 264 questions
Answer options
A: Add only the threats to the risk register
B: Utilize different tools to identify the risks
C: Plan risk responses to the threats
D: Update the risk register with the identified risks Correct answer
Correct Answer:
D. Update the risk register with the identified risks
Explanation

The SWOT (Strengths, Weaknesses, Opportunities, and Threats) analysis is a recognized data-gathering and analysis technique within the Identify Risks process. The outputs of this process, which are the identified risks, must be formally documented. The primary document for this is the risk register. The question states that opportunities (positive risks) and threats (negative risks) have been identified. Therefore, the immediate and correct subsequent action for the risk manager is to log these findings in the risk register. This step is crucial as the risk register serves as the foundational input for all subsequent risk management processes, such as qualitative and quantitative analysis and response planning.

Why Incorrect

A. The definition of risk in project management includes both positive events (opportunities) and negative events (threats). Excluding opportunities provides an incomplete view of project risk.
B. While using multiple identification tools is a best practice, the immediate next step after identifying risks with one tool is to document them, not to initiate a new identification cycle.
C. Planning risk responses is a later process that occurs only after risks have been identified, documented in the register, and then analyzed for their probability and impact.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.).

Section 11.2 Identify Risks: This section details the process of identifying individual project risks as well as sources of overall project risk and documenting their characteristics.

Section 11.2.2.4 Data Analysis: SWOT analysis is listed as a key technique used to identify risks. It states, "It examines the project from each of the SWOT perspectives to increase the breadth of identified risks by including internally generated risks as well as those arising from the environment."

Section 11.2.3.1 Risk Register: This section explicitly states that the risk register is the primary output of the Identify Risks process. "The risk register captures details of identified individual project risks."

2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.

Section 4.3 Identify Risks: This section describes the process. It notes that the output is a list of identified risks and their characteristics.

Section 4.3.3 Identify Risks: Outputs (Risk Register): "The risk register is the primary output from the Identify Risks process... As new risks are identified, they are added to the risk register." This confirms that documenting identified risks is the direct next step.

3. Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240.

Page 237, Section 3: The paper argues for a fully integrated risk process that addresses both threats and opportunities. It states, "The first step in the risk process is 'risk identification', which aims to identify all foreseeable threats and opportunities that could affect the project's ability to meet its objectives." This supports the inclusion of both in the risk register, making option A incorrect. https://doi.org/10.1016/S0263-7863(01)00074-6