PMI-RMP practice question 22 of 35

A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new…

Choose your answer, then check it against the explanation.

A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago. What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?
Answer options
Question 22 of 35

Keep practicing

Take the free PMI-RMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-RMP practice questions

Scroll to Top