PMI-RMP practice question 20 of 35
An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
Full set: 264 questionsAccelerating a project represents a significant change to a key project constraint (schedule), which fundamentally alters the project's overall risk exposure and the assumptions upon which the original risk management approach was based. The Risk Management Plan is the governing document that outlines the methodology, roles, responsibilities, timing, and risk thresholds for the project. Therefore, the first logical action for the project risk manager is to revise this plan to ensure it is aligned with the new, more aggressive timeline and the organization's potentially altered risk appetite. This revised plan will then guide all subsequent risk activities, including stakeholder engagement and updating the risk register.
A. Ensure sufficient resources are available: This is a reactive step taken after the impact of acceleration has been analyzed, not the first action in the risk management process.
C. Update the risk register: The risk register is updated with new or modified risks after the risk management framework is adjusted and new risk identification and analysis activities are performed.
D. Meet with the project's stakeholders: While essential, this action is part of the process of revising the plan and communicating changes, but the first formal step for the risk manager is to address the governing process document.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 11.1, Plan Risk Management. The guide specifies that the Risk Management Plan is the primary output that defines how risk management activities will be structured and performed. A major change to project constraints would necessitate a review and potential update to this plan before other risk activities proceed.
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Section 4.3, Plan Risk Management. This standard establishes that the risk management plan is a dynamic document. It states, "The risk management plan may be updated as needed throughout the project life cycle" in response to changes in the project environment or strategy, such as an imposed acceleration.
3. Hillson, D. (2009). Managing Risk in Projects. Gower Publishing, Ltd. Chapter 3, "The Risk Management Process," emphasizes that the initial step of the process (often called "Initiate" or "Plan") defines the scope and framework for all subsequent steps. A fundamental change to the project's objectives or constraints requires revisiting this initial step to ensure the risk process remains fit for purpose.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…