PMI-RMP practice question 19 of 35

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of…

Choose your answer, then check it against the explanation.

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices. What should the risk manager do?
Answer options
Question 19 of 35

Keep practicing

Take the free PMI-RMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-RMP practice questions

Scroll to Top