PMI-RMP practice question 19 of 35
A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of…
Full set: 264 questionsThe fundamental problem identified is the absence of a standardized risk management approach and the team's lack of familiarity with the practice. The first and most critical step in project risk management is to establish a plan that defines how risk activities will be conducted. Developing a framework and creating a risk management plan with the team's involvement directly addresses this gap. This approach, aligned with the Plan Risk Management process, ensures a consistent methodology, defines roles and responsibilities, and fosters team buy-in and understanding from the project's outset, setting the foundation for all subsequent risk activities.
A. The sponsor provides the risk appetite and approves the strategy, but the risk manager is responsible for developing the detailed risk management plan and framework.
C. Training is beneficial, but deferring the risk strategy is a critical error. The risk management plan must be established early to guide all risk identification and analysis efforts.
D. This action jumps ahead to risk analysis and response planning. It is impossible to effectively prioritize risks without first establishing the framework and criteria for doing so in the risk management plan.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.1, Plan Risk Management. This process is described as "defining how to conduct risk management activities for a project." Its primary output is the Risk Management Plan, which documents the agreed-upon framework and approach.
2. Project Management Institute. (2009). Practice Standard for Project Risk Management. Section 3.1, Plan Risk Management. This section emphasizes that the initial step is to develop and document the overall approach, including methodology, roles, responsibilities, and timing, which is encapsulated in the Risk Management Plan.
3. Hillson, D. (2002). The Risk Breakdown Structure (RBS) as an aid to effective risk management. Proceedings of the 33rd Annual Project Management Institute Seminars & Symposium. This paper implicitly supports the need for a structured approach (like an RBS), which is defined during the risk planning phase, before detailed risk identification can occur effectively.
4. Chapman, C., & Ward, S. (2003). Project Risk Management: Processes, Techniques and Insights (2nd ed.). John Wiley & Sons. Chapter 4, "Define the Process," details the necessity of establishing a clear risk management process at the project's initiation to ensure clarity, efficiency, and effectiveness. This aligns with developing a framework and plan.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…