PMI-RMP practice question 19 of 35

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of…

Full set: 264 questions
A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices. What should the risk manager do?
Answer options
A: Ask the sponsor to define the risk strategy to align with client needs.
B: Develop a framework and engage the team in creating a risk plan. Correct answer
C: Train the team on basic techniques and defer the risk strategy for later.
D: Concentrate on high-priority risks to meet the sponsor's expectations.
Correct Answer:
B. Develop a framework and engage the team in creating a risk plan.
Explanation

The fundamental problem identified is the absence of a standardized risk management approach and the team's lack of familiarity with the practice. The first and most critical step in project risk management is to establish a plan that defines how risk activities will be conducted. Developing a framework and creating a risk management plan with the team's involvement directly addresses this gap. This approach, aligned with the Plan Risk Management process, ensures a consistent methodology, defines roles and responsibilities, and fosters team buy-in and understanding from the project's outset, setting the foundation for all subsequent risk activities.

Why Incorrect

A. The sponsor provides the risk appetite and approves the strategy, but the risk manager is responsible for developing the detailed risk management plan and framework.
C. Training is beneficial, but deferring the risk strategy is a critical error. The risk management plan must be established early to guide all risk identification and analysis efforts.
D. This action jumps ahead to risk analysis and response planning. It is impossible to effectively prioritize risks without first establishing the framework and criteria for doing so in the risk management plan.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.1, Plan Risk Management. This process is described as "defining how to conduct risk management activities for a project." Its primary output is the Risk Management Plan, which documents the agreed-upon framework and approach.

2. Project Management Institute. (2009). Practice Standard for Project Risk Management. Section 3.1, Plan Risk Management. This section emphasizes that the initial step is to develop and document the overall approach, including methodology, roles, responsibilities, and timing, which is encapsulated in the Risk Management Plan.

3. Hillson, D. (2002). The Risk Breakdown Structure (RBS) as an aid to effective risk management. Proceedings of the 33rd Annual Project Management Institute Seminars & Symposium. This paper implicitly supports the need for a structured approach (like an RBS), which is defined during the risk planning phase, before detailed risk identification can occur effectively.

4. Chapman, C., & Ward, S. (2003). Project Risk Management: Processes, Techniques and Insights (2nd ed.). John Wiley & Sons. Chapter 4, "Define the Process," details the necessity of establishing a clear risk management process at the project's initiation to ensure clarity, efficiency, and effectiveness. This aligns with developing a framework and plan.