PMI-RMP practice question 12 of 35
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager…
Choose your answer, then check it against the explanation.
One project in a program needs to be completed in 6 months because there is a large bonus for early
completion. Consequently, the program manager transfers all resources to this project and arranges
for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
Question 12 of 35
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 3A project lihat was in the execution phase for the last six months was put on hold and wa…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6A risk management professional is currently facilitating the risk planning process with t…
