PMI-RMP practice question 12 of 35

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager…

Choose your answer, then check it against the explanation.

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay. Which risk response strategy is the program manager using in this scenario?