PMI-RMP practice question 13 of 35
During a project's initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor…
Choose your answer, then check it against the explanation.
During a project's initial planning session, the project team identifies a possible risk. The team is
under the impression that a critical vendor might delay delivery. This could impact both the project
schedule and budget. The team shares insights on the risk's likelihood and impact with the risk
manager.
What should the risk manager do?
Question 13 of 35
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 3A project lihat was in the execution phase for the last six months was put on hold and wa…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6A risk management professional is currently facilitating the risk planning process with t…
