PMI-RMP practice question 14 of 35
What should the risk owner use as an effective information-gathering technique during the planning session?
Full set: 264 questionsBrainstorming is a fundamental information-gathering technique used during the Identify Risks process, which is a core part of risk management planning. In a planning session, it facilitates a collaborative environment where team members, stakeholders, and the risk owner can generate a comprehensive list of potential project risks. This group creativity technique encourages open communication and leverages the collective knowledge and experience of the participants to uncover a broad spectrum of risks that might be missed by an individual.
A. Monte Carlo analysis: This is a quantitative analysis technique used to model the combined effect of risks on project objectives, not a method for gathering initial risk information.
B. Update risk register: This is the action of documenting risks after they have been identified; it is an output of the process, not an information-gathering technique itself.
D. Cost and time estimating: These are planning processes that produce estimates. While the process of estimating can reveal risks, they are not primary information-gathering techniques for risk identification.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute. Section 11.2.2.1, p. 415. This section explicitly lists brainstorming as a data-gathering technique for the "Identify Risks" process, describing it as a method to obtain a comprehensive list of individual project risks.
2. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects. Project Management Institute. Section 4.3.3, p. 48. Table 4-2 lists brainstorming as a common tool and technique for the "Identify Risks" process.
3. Hillson, D. (2003). Using a risk breakdown structure in project management. Journal of Facilities Management, 2(1), 85-97. https://doi.org/10.1108/14725960410808231. The article discusses the Risk Breakdown Structure (RBS) as a framework to facilitate comprehensive risk identification, a process often initiated through techniques like brainstorming.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…