Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

Full set: 327 questions
Answer options
A: Contract
B: Reserve analysis Correct answer
C: Scope baseline
D: Project schedule
Correct Answer:
B. Reserve analysis
Explanation

Reserve analysis is not an input to the determine budget process. It is a technique used for determining the budget. The inputs to the determine budget process are as follows: Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calendars Contracts Organizational process assets