PMI-SP practice question 7 of 35
Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?
Full set: 327 questionsBy adding lag time to the carpet activity, Joe can move the start time of the carpet activity by 30 hours. A lag time is a delay between the predecessor and the successor tasks. Sometimes it may be needed to schedule a delay between the predecessor and the successor tasks. For example, if two coats of paint are required to paint a car, then the final coat should be applied only when the first coat dries. This delay is known as the lag time. The lag time is entered as a positive value. The lag time can be entered as a duration or as a percentage of the predecessor's task duration. It is entered on the Predecessor tab in the Task Information dialog box. Answer option A is incorrect. A lead time is the time that overlaps between the predecessor and the successor tasks. The successor task can start before the predecessor task finishes. Answer option C is incorrect. Dummy activities are not the preferred method of project scheduling. Answer option B is incorrect. Changing the relationship of the activity to finish-to-finish would not prevent the activities from overlapping.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 8The Define Activities process is the first process in the project time management knowled…
- Question 9You are the project manager for your organization. You are meeting with your customers to…
