Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting…

Choose your answer, then check it against the explanation.

Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?