PMI-SP practice question 2 of 35

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Full set: 327 questions
Answer options
A:

A. Procurement document

B:

B. Contract

C:

C. Business case

D:

D. Project statement of work

Correct answer
Correct Answer:
<P>B; D. D. Project statement of work; AND C</P>
Explanation

The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows: Project statement of work Business case Contract Enterprise environmental factors Organizational process assets The output of the Develop project Charter process is as follows : Project charter Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders process.

Scroll to Top