You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team. What type of communication method are you using in this instance?

Full set: 327 questions
Answer options
A: Interactive communication Correct answer
B: Active communication
C: Pull technique
D: Push technique
Correct Answer:
A. Interactive communication
Explanation

Any meetings, phone calls with multiple participants, or conferences are examples of the interactive communications. Answer option B is incorrect. Active communication is not a PMBOK term for project management. Answer option D is incorrect. A push technique describes a distribution from the project manager out to the message recipients, such as email. Answer option C is incorrect. A pull technique describes a distribution method where the recipients of the message pull the message from a source, such as a Web server.

Scroll to Top