Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be…
Full set: 327 questionsResource leveling is a rule of limiting the total number of hours a project team may work during a given time period in the project. If management restricts the project work to 45 per week, as in this example, Holly's schedule will likely increase because the project team can't complete as much work in one given time period.While this may be seen as a constraint, because it limits Holly's options, it's technically called a resource leveling heuristic. Answer option B is incorrect. It is an assumption that's believed to be true, but it hasn't been proven to be true. Answer option C is incorrect. Execution variance analysis describes the difference between what was planned and what was executed. A better term for this experience would simply be a scope variance, scope change, or defect.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
- Question 9You are the project manager for your organization. You are meeting with your customers to…