PRINCE2-PRACTITIONER practice question 22 of 35
Project Scenario Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of…
Full set: 290 questionsDomain Apply and tailor the PRINCE2 processes in context
The forecast delay in completing the customer list is a deviation from the plan. In PRINCE2, a relevant event that has happened or is forecast to happen, was not planned, and requires management action is defined as an 'issue'. Specifically, this is an 'off-specification' because a product will not be delivered as planned. The correct procedure for any team member who identifies such a deviation is to raise an issue immediately to inform the Project Manager. This allows the Project Manager to log, assess the impact, and decide on the appropriate corrective action in a timely manner.
A. Checkpoint Reports are sent from the Team Manager to the Project Manager, not the Executive, and waiting for the next report may delay necessary action.
B. A team member does not have the authority to modify or add products to a Stage Plan; this is the responsibility of the Project Manager.
C. The event is a forecast certainty ("will NOT be complete"), not an uncertain event. Therefore, it is an issue, not a risk.
1. AXELOS
Managing Successful Projects with PRINCE2
6th Edition. The Stationery Office (TSO)
2017.
Correct Answer (D): Section 10.2.1 defines an issue
including an off-specification
as an event that has happened and requires management action. Section 18.4.5
"Capture and examine issues and risks
" states that issues can be raised at any time by anyone on the project
and the first step is to capture them for the Project Manager's review.
Incorrect Option (A): Appendix A.4
"Checkpoint Report
" specifies that this report is used by a Team Manager to provide progress information to the Project Manager
not the Executive.
Incorrect Option (B): Chapter 19
"Managing a Stage Boundary
" details that creating the next Stage Plan (Section 19.4.3) is a Project Manager's responsibility
subject to Project Board approval.
Incorrect Option (C): Section 11.2.1 defines a risk as "an uncertain event
" which contrasts with an issue. The scenario describes a certain deviation
making it an issue.
Keep practicing
Take the free PRINCE2-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-PRACTITIONER practice questions
- Question 2Scenario A photographer from Portraits Ltd, a professional photographic company, has take…
- Question 6Which of the following statements is TRUE with regard to expected benefits?
- Question 8Scenario Additional Information Chief Executive Officer (CEO): He started the company 25 …
- Question 10Who sets the tolerances for a work package?
- Question 11Scenario Additional Information During the initiation stage the Project Manager met with …
- Question 12When considering the business options in the business case, which of these is NOT an opti…