PRINCE2-PRACTITIONER practice question 11 of 35
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the…
Full set: 290 questionsDomain Apply and tailor the PRINCE2 processes in context
A Business Case risk is an uncertain event that, if it occurs, would threaten the project's viability and the achievement of its benefits. The Business Case for this project is justified by the expected increase in customer orders.
Option C describes the risk that poor quality could lead to a reduction in orders, directly undermining the project's primary benefit and business justification.
Option D addresses a key assumption mentioned in the scenario. If competitors increase their marketing activity, the project's benefits will be reduced, which directly threatens the viability of the Business Case. Both are significant threats to the project's core objectives and would be classified as major risks.
A. This is a dis-benefit or a follow-on cost resulting from the project's success, not an uncertain event (risk). It should be factored into the Business Case calculations.
B. This is a project requirement or milestone. The associated risk would be the failure to meet this deadline, but the statement itself is not a risk.
E. This is a stated project benefit. The corresponding risk would be the failure to improve staff morale, but the statement as written is a positive outcome.
1. AXELOS
"Managing Successful Projects with PRINCE2® 2017 Edition"
The Stationery Office.
Section 10.1
p. 127: Defines a risk as "an uncertain event or set of events that
should it occur
will have an effect on the achievement of objectives." This supports why options B and E are incorrect as they are not framed as uncertain events.
Section 6.1
p. 31: The purpose of the Business Case theme is "to establish mechanisms to judge whether the project is (and remains) desirable
viable and achievable as a means to support decision-making". Risks C and D directly threaten the project's desirability and viability.
Section 6.2.1
p. 32: The Business Case must document the justifiable reasons for the project. It must also include the major risks. Options C and D are major risks to the justification.
Section 6.3.3
p. 35: Defines a dis-benefit as "an outcome that is perceived as negative by one or more stakeholders." The increased operational cost (Option A) is a dis-benefit
not a risk.
Keep practicing
Take the free PRINCE2-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-PRACTITIONER practice questions
- Question 2Scenario A photographer from Portraits Ltd, a professional photographic company, has take…
- Question 6Which of the following statements is TRUE with regard to expected benefits?
- Question 8Scenario Additional Information Chief Executive Officer (CEO): He started the company 25 …
- Question 10Who sets the tolerances for a work package?
- Question 12When considering the business options in the business case, which of these is NOT an opti…
- Question 16Scenario: The Ministry of Food Hygiene (MFH) has a quality management system which contai…