PRINCE2-PRACTITIONER practice question 16 of 35
Scenario: The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation…
Full set: 290 questionsDomain Apply and tailor the PRINCE2 processes in context
The question asks to identify an additional risk placed on the project due to using the corporate configuration management procedure. Options B and C are not risks: B describes an issue (a certain event), and C describes a constraint (a statement of fact). Option D describes a risk but for a different project ('Outsourcing project'). By elimination, A is the correct answer. According to PRINCE2, projects should align with and leverage existing corporate or programme management standards. Using a mature, established corporate document control process is considered good practice that reduces uncertainty and risk, rather than adding to it. Therefore, this arrangement introduces no additional risk.
B. This statement describes a specific delay, which is an issue or a forecast, not a risk. A risk is an uncertain event that may or may not happen.
C. This is a statement of fact about the project's financial status. It is a project constraint, not an uncertain future event (a risk).
D. This describes a valid risk, but it is explicitly for the 'Outsourcing project', not the 'Restructuring project' that is the subject of the scenario.
1. AXELOS
"Managing Successful Projects with PRINCE2
7th Edition" (2023).
Section 11.1
What is risk?: Defines a risk as "an uncertain event or set of events that
should it occur
will have an effect on the achievement of objectives." This definition confirms that options B (an issue) and C (a constraint) are not risks.
Section 4.2.2
Corporate or programme standards: States
"The project management team should adopt the organization’s standards... Using the organization’s standards will reduce the work for the project and will mean that the project’s outputs are more easily integrated into the organization’s business as usual." This supports the rationale that using the corporate system is a risk-reducing measure
thus adding no additional risk.
Appendix A
Section A.5
Configuration management procedure: Notes that the project's procedure should detail how it aligns with any "corporate or programme management quality or configuration management systems." This reinforces that compliance is expected and not inherently a risk.
Keep practicing
Take the free PRINCE2-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-PRACTITIONER practice questions
- Question 2Scenario A photographer from Portraits Ltd, a professional photographic company, has take…
- Question 6Which of the following statements is TRUE with regard to expected benefits?
- Question 8Scenario Additional Information Chief Executive Officer (CEO): He started the company 25 …
- Question 10Who sets the tolerances for a work package?
- Question 11Scenario Additional Information During the initiation stage the Project Manager met with …
- Question 12When considering the business options in the business case, which of these is NOT an opti…