PRINCE2-PRACTITIONER practice question 10 of 35
Who sets the tolerances for a work package?
Full set: 290 questionsDomain Apply and tailor the PRINCE2 processes in context
According to the PRINCE2 methodology, there is a clear hierarchy for setting tolerances, which enables the 'Manage by Exception' principle. The Project Board sets stage-level tolerances for the Project Manager. The Project Manager, in turn, is responsible for the day-to-day management of the stage and authorizes work to be done by Team Managers through Work Packages. As part of authorizing a Work Package, the Project Manager sets the tolerances for time, cost, scope, quality, risk, and benefits for that specific package of work. These Work Package tolerances must be within the overall stage tolerances.
A. The project board: The Project Board sets tolerances for each management stage and delegates the day-to-day management of that stage to the Project Manager.
C. The team manager: The Team Manager accepts the Work Package and is responsible for delivering its products within the tolerances set by the Project Manager.
D. Corporate or programme management: This level of management sets the overall project-level tolerances for the Project Board, not the detailed Work Package tolerances.
1. AXELOS. (2017). Managing Successful Projects with PRINCE2 (6th ed.). TSO (The Stationery Office).
Section 10.2.2
Tolerances
Figure 10.2 ‘Levels of tolerance’: This diagram explicitly shows that the Project Manager sets Work Package tolerance for the Team Manager.
Section 18.4.1
‘Authorize a Work Package’: This section details the activity where the Project Manager agrees on the constraints
including tolerances
for a Work Package with a Team Manager.
Appendix A
Section A.20.2
‘Project Manager responsibilities’: States the Project Manager is responsible to "Agree the Work Package with the Team Manager". This agreement includes defining and setting the tolerances.
Keep practicing
Take the free PRINCE2-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-PRACTITIONER practice questions
- Question 2Scenario A photographer from Portraits Ltd, a professional photographic company, has take…
- Question 6Which of the following statements is TRUE with regard to expected benefits?
- Question 8Scenario Additional Information Chief Executive Officer (CEO): He started the company 25 …
- Question 11Scenario Additional Information During the initiation stage the Project Manager met with …
- Question 12When considering the business options in the business case, which of these is NOT an opti…
- Question 16Scenario: The Ministry of Food Hygiene (MFH) has a quality management system which contai…