PRINCE2-PRACTITIONER practice question 8 of 35
Scenario Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg…
Choose your answer, then check it against the explanation.
Domain Apply effective people management in successful projects
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He
injured his leg two years ago which has restricted his visits to the engineering are
a. As CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career
with a publicity company. She has the ability to represent the needs of the business, particularly as
this is a marketing project. She has the authority to commit the annual business marketing budget,
from which the project will be funded, as she sees appropriate. She will be responsible for
monitoring the expected benefits of the calendar, in particular the improvement of the company's
image.
Engineering Manager: He has been responsible for many engineering innovations in the company
and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team,
his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They
now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers
and a history of successful work. This company has been selected to take the photos for the company
calendar. It has yet be decided which of the photographers to use.
Which 2 statements explain why the Marketing Director should be appointed as the Executive for this
project?
Question 8 of 35
Keep practicing
Take the free PRINCE2-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-PRACTITIONER practice questions
- Question 2Scenario A photographer from Portraits Ltd, a professional photographic company, has take…
- Question 6Which of the following statements is TRUE with regard to expected benefits?
- Question 10Who sets the tolerances for a work package?
- Question 11Scenario Additional Information During the initiation stage the Project Manager met with …
- Question 12When considering the business options in the business case, which of these is NOT an opti…
- Question 16Scenario: The Ministry of Food Hygiene (MFH) has a quality management system which contai…