RCDDV14.1 practice question 24 of 35
A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has…
Full set: 320 questionsResource leveling is the standard program management technique for addressing resource constraints while balancing the triple constraints of time, budget, and quality. When faced with unavailable resources, a program manager must optimize resource allocation across the program's components, potentially adjusting schedules, reassigning tasks, or finding alternative resources while maintaining program objectives. This approach allows the program to proceed while managing constraints systematically rather than making compromised decisions that could jeopardize quality or success.
A. Utilizing unqualified resources compromises quality and increases project risk, violating professional standards.
B. Focusing only on critical path ignores overall program dependencies and resource optimization opportunities.
C. Delaying the entire program may be unnecessary when resource leveling can address constraints effectively.
1. PMBOK Guide 7th Edition, Section 2.6.3 "Resource Management" - Project Management Institute
2. "Program Management Professional (PgMP) Standard" 4th Edition, Chapter 6.4 "Resource Planning and Management" - PMI
3. BICSI Telecommunications Project Management Manual, Chapter 8 "Resource Management in Technology Programs"
4. IEEE Standard 1490-2011 "Guide for Program Management", Section 5.3.2 "Resource Optimization Techniques"
5. ISO 21502:2020 "Project, programme and portfolio management", Section 4.3.17 "Resource management processes"
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 4The program manager wants to ensure that a program contributes to shareholder value. The …
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…