A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has…

Full set: 320 questions
A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program As a result, the program manager must do which of the following'?
Answer options
A: Utilize team members that are currently available, even though they do not have the expertise needed.
B: Assign the tasks on the critical path to the resources available to adhere to the project schedule
C: Delay the start of the program until the assigned resources are available
D: Apply resource leveling considering the constraints of time, budget, and quality Correct answer
Correct Answer:
D. Apply resource leveling considering the constraints of time, budget, and quality
Explanation

Resource leveling is the standard program management technique for addressing resource constraints while balancing the triple constraints of time, budget, and quality. When faced with unavailable resources, a program manager must optimize resource allocation across the program's components, potentially adjusting schedules, reassigning tasks, or finding alternative resources while maintaining program objectives. This approach allows the program to proceed while managing constraints systematically rather than making compromised decisions that could jeopardize quality or success.

Why Incorrect

A. Utilizing unqualified resources compromises quality and increases project risk, violating professional standards.
B. Focusing only on critical path ignores overall program dependencies and resource optimization opportunities.
C. Delaying the entire program may be unnecessary when resource leveling can address constraints effectively.

References

1. PMBOK Guide 7th Edition, Section 2.6.3 "Resource Management" - Project Management Institute

2. "Program Management Professional (PgMP) Standard" 4th Edition, Chapter 6.4 "Resource Planning and Management" - PMI

3. BICSI Telecommunications Project Management Manual, Chapter 8 "Resource Management in Technology Programs"

4. IEEE Standard 1490-2011 "Guide for Program Management", Section 5.3.2 "Resource Optimization Techniques"

5. ISO 21502:2020 "Project, programme and portfolio management", Section 4.3.17 "Resource management processes"