RCDDV14.1 practice question 25 of 35

An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review What should the program manager do next?

Full set: 320 questions
Answer options
A: Assign resources lo the schedule and report the revised delivery date to the project managers
B: Work with the project managers to refine the project schedules and deliverables to align with the program milestones Correct answer
C: Revise the project schedules to meet the program schedule and communicate to stakeholders
D: Integrate the project schedules into the program schedule and report the revised delivery date to the project managers
Correct Answer:
B. Work with the project managers to refine the project schedules and deliverables to align with the program milestones
Explanation

After receiving preliminary schedules from project managers, the program manager should collaborate with them to refine schedules and deliverables to align with program milestones. This collaborative approach ensures buy-in, identifies dependencies, and maintains realistic timelines while working toward the accelerated market delivery goal. Direct collaboration allows for optimization of resources and schedules across projects while respecting the expertise of individual project managers.

Why Incorrect

A. Simply assigning resources without collaboration bypasses critical alignment discussions and may create unrealistic expectations.
C. Unilaterally revising schedules without project manager input ignores ground-level constraints and risks creating unachievable timelines.
D. Merely integrating schedules without refinement fails to address the acceleration requirement and potential conflicts between projects.

References

- PMI's "The Standard for Program Management" (4th Edition), Chapter 6: Program Schedule Management, pp. 89-92

- IEEE Guide to the Software Engineering Body of Knowledge (SWEBOK V3.0), Chapter 7: Software Engineering Management, Section 7.2

- MIT OpenCourseWare: "Project Management Principles" (15.387), Module 4: Multi-Project Coordination

- ISO 21500:2012 "Guidance on Project Management," Section 4.3.12: Schedule Development

- PMBOK Guide (7th Edition), Section on Portfolio and Program Alignment, pp. 156-158

Scroll to Top