RCDDV14.1 practice question 25 of 35
An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review What should the program manager do next?
Full set: 320 questionsAfter receiving preliminary schedules from project managers, the program manager should collaborate with them to refine schedules and deliverables to align with program milestones. This collaborative approach ensures buy-in, identifies dependencies, and maintains realistic timelines while working toward the accelerated market delivery goal. Direct collaboration allows for optimization of resources and schedules across projects while respecting the expertise of individual project managers.
A. Simply assigning resources without collaboration bypasses critical alignment discussions and may create unrealistic expectations.
C. Unilaterally revising schedules without project manager input ignores ground-level constraints and risks creating unachievable timelines.
D. Merely integrating schedules without refinement fails to address the acceleration requirement and potential conflicts between projects.
- PMI's "The Standard for Program Management" (4th Edition), Chapter 6: Program Schedule Management, pp. 89-92
- IEEE Guide to the Software Engineering Body of Knowledge (SWEBOK V3.0), Chapter 7: Software Engineering Management, Section 7.2
- MIT OpenCourseWare: "Project Management Principles" (15.387), Module 4: Multi-Project Coordination
- ISO 21500:2012 "Guidance on Project Management," Section 4.3.12: Schedule Development
- PMBOK Guide (7th Edition), Section on Portfolio and Program Alignment, pp. 156-158
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 4The program manager wants to ensure that a program contributes to shareholder value. The …
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…