RCDDV14.1 practice question 26 of 35

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress"?

Full set: 320 questions
Answer options
A: Define the key performance indicators (KPIs) for the program's outcome Correct answer
B: Invite the key stakeholder to review the program charter and the program objectives
C: Provide additional program performance reports to the key stakeholder
D: Maintain the benefits register and provide it to the key stakeholder
Correct Answer:
A. Define the key performance indicators (KPIs) for the program's outcome
Explanation

To demonstrate a program's progress toward its objectives, the program manager should use objective measures. Defining and tracking Key Performance Indicators (KPIs) is the most effective method. KPIs are quantifiable metrics that directly measure performance against the program's strategic objectives and desired outcomes. Presenting progress based on these pre-defined KPIs provides the stakeholder with clear, data-driven evidence of how the program is performing and advancing toward its goals, rather than relying on static documents or generic reports.

Why Incorrect

B. The program charter states the objectives but does not provide any information on the current progress toward achieving them.
C. Providing more reports is not useful unless the reports contain the right information, which is best represented by KPIs.
D. The benefits register tracks potential benefits but does not directly measure the delivery progress of the work required to achieve them.

References

1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 6.4, Program Benefits Monitoring and Control, p. 106. (Emphasizes the use of metrics and KPIs to monitor progress toward intermediate benefits and outcomes).

2. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 3.5, Program Monitoring and Control Domain, p. 46. (States this domain includes "monitoring progress to determine the current state of the program" using performance measures).