RCDDV14.1 practice question 26 of 35
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress"?
Full set: 320 questionsTo demonstrate a program's progress toward its objectives, the program manager should use objective measures. Defining and tracking Key Performance Indicators (KPIs) is the most effective method. KPIs are quantifiable metrics that directly measure performance against the program's strategic objectives and desired outcomes. Presenting progress based on these pre-defined KPIs provides the stakeholder with clear, data-driven evidence of how the program is performing and advancing toward its goals, rather than relying on static documents or generic reports.
B. The program charter states the objectives but does not provide any information on the current progress toward achieving them.
C. Providing more reports is not useful unless the reports contain the right information, which is best represented by KPIs.
D. The benefits register tracks potential benefits but does not directly measure the delivery progress of the work required to achieve them.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 6.4, Program Benefits Monitoring and Control, p. 106. (Emphasizes the use of metrics and KPIs to monitor progress toward intermediate benefits and outcomes).
2. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 3.5, Program Monitoring and Control Domain, p. 46. (States this domain includes "monitoring progress to determine the current state of the program" using performance measures).
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 4The program manager wants to ensure that a program contributes to shareholder value. The …
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…